No Able To Baseline Budgets That Have Project Manager Start Dates In The Future

(Doc ID 2209028.1)

Last updated on OCTOBER 24, 2017

Applies to:

Oracle Fusion Grants Management Cloud Service - Version 11.1.11.1.0 and later
Oracle Fusion Grants Management - Version 11.1.11.1.0 and later
Information in this document applies to any platform.

Symptoms

Not able to baseline budgets that have project manager start dates in the future

Cause

Sign In with your My Oracle Support account