My Oracle Support Banner

SOP Plan With 2 Year Horizon Completes In Error (Doc ID 2380369.1)

Last updated on MARCH 29, 2018

Applies to:

Oracle Sales and Operations Planning Cloud Service - Version 11.13.17.11.0 and later
Information in this document applies to any platform.

Symptoms


When the S&OP Plan is run the Demand Plan portion completes in error with the message:

ERROR
 "At least one forecasting profile date is invalid. Check demand forecasting profiles in plan options."


STEPS TO REPRODUCE
1. Define a S&OP Plan with a 2 Year (730 day) Horizon.
2. The Gregorian Calendar has been built to cover a 20 year time span beyond the plan run date.
3. Run the S&OP Plan
4. Hit the error.



Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.