Item Cost Rollup for Setting up Standard Lot SizeAattribute
(Doc ID 2522627.1)
Last updated on AUGUST 16, 2022
Applies to:
Oracle Fusion Cost Management - Version 11.12.1.0.0 and laterOracle Fusion Cost Management Cloud Service - Version 11.13.19.07.0 and later
Oracle Fusion Inventory Management Cloud Service - Version 11.13.19.07.0 and later
Information in this document applies to any platform.
Goal
What is the impact on Item Cost rollup for setting up Standard Lot Size attribute at Item Master.
Example:
User have a finishgood FG1 with components C1 and C2.
now, for C2 component user want to set the Standard Lot Size 2000 at Item master level. (Manufacturing > Costing)
In bills of material C2 usage is defined as 2 fixed. In Cost Scenario have defined Std Cost as 10 USD.
Once we do the rollup we are expecting that the unit cost for C2 should be calculated as (Qty/Lot Size) *Std Cost
(2/2000) * 10 which is not happening in the current application.
System is simply multiplying Qty*Std Cost = 2*10 = 20 USD
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |