Dependent Demand For BOM Level 2 Components Not Exploded Correctly
(Doc ID 2575390.1)
Last updated on AUGUST 24, 2020
Applies to:
Oracle Supply Planning Cloud Service - Version 11.13.19.04.0 and laterInformation in this document applies to any platform.
Goal
Dependent demand for Item Structure level 2 components not exploded correctly
Second level Item Structure component demand is 5 times more that what is defined in the Item Structure.
As a part of basic testing there is a 2 level Item Structure.
The BOM explosion for level 1 components is correct (1;1) whereas the next level it gets multiplied by 5 times.
Solution