Unconstrained Supply Planning: Planned Orders Information and Troubleshooting Document
(Doc ID 2655590.1)
Last updated on MAY 18, 2023
Applies to:
Oracle Supply Planning Cloud Service - Version 11.13.17.05.0 and laterInformation in this document applies to any platform.
Purpose
This Document provides information about Planned Orders and related setups, Common Issues, Frequently asked questions (FAQ) and Troubleshooting tips.
Scope
The functionality described on this document is applicable to Fusion Supply Planning Cloud
Details
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Purpose |
Scope |
Details |
General Information |
Planned Order Scheduling |
Planned Order Dates |
Supply Planning Calendars |
Releasing Planned Orders |
Order Modifiers |
REST API for Planned Orders |
Frequently Asked Questions |
How to search released planned order in SCO? |
How to restrict release of planned order |
How to see monetary value of planned order? |
How Planned Orders are created in case of sourcing split? |
Can we release Purchase Requisition in firm status from Planning? |
With what time stamp, planned order is released from Planning? |
How to use alternate work definition in planned orders? |
Which calendar is used for OSP operations? |
What release action "Release Reservation" means for planned order? |
What is the maximum number of planned orders created for specific item in an organization in the same day? |
What is the use of Plan option "Released only by user”? |
Is Planner mandatory to release planned order? |
Is it possible to convert a planned order with a type of BUY to a type of TRANSFER? |
Why plan output is not matching for the weekly buckets of two different plans with same plan options? |
Why planned orders created in an unconstrained supply plan not considering lead time demand? |
Can we have Same operation Sequence with multiple Effective dates in Planing ? Will Plan Considers all of them while calculating Plan Orders? |
In ASCP on premises, Req Group By was able to be set in User Preferences. What is the equivalent of this in Supply Planning Cloud ?? |
Why is user unable to see planned orders get created under supplies and demand table? This was working as expected previously, now it is only visible for couple of items. |
Common Issues & Errors |
Planned Order released status is Ineligible |
Component Demands not getting calculated. |
Duplicate planned orders created and pegged to end assembly item |
After releasing the planned orders from a fusion source plan (OPS) supply orders are not getting created in supply chain orchestration. |
Supply Plan Does Not Respect Supplier Shipping Calendar. As per Calendar definition ,supplier ship date (suggested ship date) should be only on Mondays. |
Suggested Due Date not showing correct date as per the time zone. |
Planned orders not generating for some of the components of BOM/assembly. |
Alternate Resource not honored in Work Order |
Plan is trying to create make plan order for Buy Items |
Released planned orders regenerating again after plan was rerun with the same planned order number with slightly different quantity in firm status. |
Dock Date for Transfer Order in the Destination Org is 1 day earlier than the Suggested Due Dates for the Planned Orders for the Make Items in the Source Org (BLR). |
When releasing firm qty more than planned order quantity, Release recommendation file is not showing firm quantity instead it shows plan order quantity. |
Order Modifiers such as Fixed Order Quantity (FOQ) and Fixed Lot Size Multiplier (FLM) are not honored by plan. |
Planned Orders released from Planning to Supply Chain Orchestration (SCO) hit the following error in SCO for two or more Orgs: "The deliver-to organization is not assigned to the requisitioning BU" |
Work Order Creation Failed after releasing the Planned Make Order from Planning. Error in SCO: "The value of the attribute INVENTORY_ITEM_ID is not valid" |
Planned Order Release Fails in SCO with error: "There are no valid work definitions or versions defined for the specified date and item" |
Why is total demand not equal to total supply? |
User is receiving following error when releasing manually created planned orders for the same supplier but different sites together? |
For Buy Planned Orders, the Implementation Date updated in Planning is not updating as Requested Delivery Date in PO. |
Planned Orders: Suggested Start Date occurring on a Saturday (non-working day). |
Planned Order not created for lower level items. Plan messages show MSC_PCENG_SOURC_LOOP_BROKEN. |
Single planned order being created for demand from three different tasks of a project? |
Non-Standard Work Order is not Pegged to any Demand, instead new planned orders are created and pegged to demand. |
Planned order for item with shrinkage is not rounded when rounding item attribute is selected. |
Some planned orders have start dates 1 day in the past. |
Demand is not flowing to Supplier Modeled Organization |