Incorrect Previous Week Commit Values Rolled Up When Collaboration Plan Cycle Changes (Doc ID 2672804.1)

Last updated on JUNE 19, 2020

Applies to:

Oracle Supply Chain Collaboration Cloud Service - Version 11.13.20.01.0 and later
Information in this document applies to any platform.

Symptoms

Incorrect previous week commit values rolled up when collaboration plan cycle changes.

Steps followed:

1. Collaboration plan defined: Plan frequency> 1 week, start day: Wednesday

2. Uploaded first forecast on Tuesday 17 Mar- all values were okay. Published forecast, submitted supplier commit, changed commit value for one week.

3. Uploaded second forecast on Wednesday 18 Mar - the commit values rolled up to previous week

4. ISSUE: the rolled up values do not look ok. The week where the commit value was modified, the roll up value is zero.

 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
 




 