PRC:PO: Cannot Submit a Negative Change Order to Decrease the Amount of a PO Due to Error: The Distribution Failed Funds Check. Budget Period Closed for Control Budget. (Doc ID 2676691.1)

Last updated on SEPTEMBER 06, 2024

Applies to:

Oracle Fusion Purchasing Cloud Service - Version 11.13.20.04.0 and later
Oracle Fusion Purchasing - Version 11.13.20.01.0 and later
Information in this document applies to any platform.

Symptoms

When submitting a Change Order to decrease the amount of a Purchase Order (PO), a failed Funds Check error is received due to the Budget Period being closed for Budget Control. A Change Order with a closed Budget Period fails Funds Check. Therefore a negative Change Order cannot be entered.

Example: FEB-20 period needs to be open in order to put money back in the MAY-20 period account, but the FEB-20 period is closed. 

ERROR
-----------------------
The distribution failed funds check.
Budget Period closed for control budget.



STEPS TO REPRODUCE
-------------------------
1. Procurement > Purchase Orders
2. Create Purchase Order
-Verify Purchase order has a budget date in a open budget period (or use a PO that was created in a previous open budget period that is already approved)
3. Get the PO approved and in Open/Reserved Status
4. Close the budget period at month end
5. Create a Change Order for the PO
6. Decrease the amount of the PO but DO NOT Close
7. Receive a failed funds check stating the Control Budget is closed

 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.