Planned Dates Are Not Recalculated If The Lead Time In The Backlog Planning Rules Is Changed (Doc ID 2715876.1)

Last updated on MARCH 12, 2021

Applies to:

Oracle Supply Planning Cloud Service - Version 11.13.20.04.0 and later
Information in this document applies to any platform.

Symptoms

When updating the field "User-defined Lead Time in Days" in Backlog Planning Rule Criteria user-interface, then refreshing the plan, the lead time attribute is not reflected in plan results.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Go to Backlog Management work area
2. Tasks
3. Manage Backlog Planning Rules
4. Update Rule ATP for BM with Lead Time
5. Open plan
6. Run plan
7. See results

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.