Constrained Planning: Planned Order Information and Troubleshooting Document (Doc ID 2787625.1)

Last updated on FEBRUARY 18, 2023

Applies to:

Oracle Supply Planning Cloud Service - Version 11.13.19.10.0 and later
Information in this document applies to any platform.

Purpose

 This document provides information about Constrained Supply Planning Planned order Information and troubleshooting document.

Scope

 The functionality described in this document is applicable to Fusion Constrained Supply Planning Cloud.

Details

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
Scope
Details
  Frequently Asked Questions
 Where can we learn how to set up and run constrained plans as well as understand the output of constrained plans?
 Why buy type planned orders not considering transit lead time in constrained plan output?
 Why system is not generating planned order demand for components of a BOM if we do not have on-hand in a constrained supply planning?
 How can we explain the start date and end date for work order based on Resource Overloading?
 Can planned orders still be created if Create Supply Flag for an item is set to No?
 Why is Processing Lead Time Added to Planned Order when it is defined as 0?
 How to search for all the “Planned Orders” eligible for release linking to the Sales Orders due in next 7 days?
 Why planned order loaded through FBDI is not visible in a plan?
 Why planned orders were not created for one item, but they are created for a different item?
 Why implement date for plan orders is different in planning recommendations output CSV file compared to plan order Suggested due date in UI?
 Why is a Firm Planned Order gets priority over a Sales Order with earlier due date?
 Common Issues & Errors
 Planning generates planned orders for both primary and alternate components without consuming supply for primary component
 Plan Not considering work definition for offsetting start and end dates of make planned order
 Excess planned order quantity is generated which is pegged to no demands
 Planned Orders of Co products and By products are not shown in the plan for process manufacturing.
 Plan not generating the resource requirements for planned order.
 Plans not considering the order modifiers for planned order quantities.
 Plan is creating planned order requirement for primary components as well alternate components instead of using the current on-hand for alternate components.
 Plan generates a single large quantity for multiple demands leading resource overload.
 Plan Considering resource calendar
 Existing Transfer order is suggested to be cancelled and new planned orders is being generated instead of using the existing supply to satisfy the demand.
 Supply plan cancels existing work orders and creates make planned orders to satisfy the demands.
 Planned orders not generated for manual demand created in a simulation set
 Constraint planning uses substitute component even though primary item quantity is available
 The Constrained plan is recommending pre building of Planned Orders of FG Item for the entire plan timeframe based on the effectivity end date of Component A. It is completely ignoring the fact that another component is effective from the next day till the end of plan timeframe.
 Planned orders are not getting generated for external forecast.
 Planning creates multiple planned orders even without any order modifiers.
 Planned order suggested start date is on a Saturday which is off day.
 Planned order is not created for the safety stock demand on the day of lot expiration for the on hand quantity.
 A make item has demand, no onhand and has all the required setups (BOM, Work definition of type process) but not generating planned order.
 Planning Time Fence Not Getting Honored For Make Order Suggested Start Date