Symptoms
When upgrading Ethernet-based PCC from 2.4.1 to 2.4.2 with pca_upgrader-1.2-111.el6, it fails on precheck:
[2020-09-20 10:22:15 17026] ERROR (precheck:148) [Network Configuration Check (Verifying that the network interfaces are configured correctly on the management nodes and compute nodes)] Failed
The check succeeded on the management nodes. The check failed on the following compute nodes: ['ovcacn09r1', 'ovcacn07r1', 'ovcacn08r1', 'ovcacn10r1']. Compute node ovcacn09r1: ovcacn09r1: bond0 inet cannot be verified.
ovcacn09r1 Network Configuration Analysis -- FAIL Compute node ovcacn07r1: ovcacn07r1: bond0 inet cannot be verified.
ovcacn07r1 Network Configuration Analysis -- FAIL Compute node ovcacn08r1: ovcacn08r1: bond0 inet cannot be verified.
ovcacn08r1 Network Configuration Analysis -- FAIL Compute node ovcacn10r1: ovcacn10r1: bond0 inet cannot be verified.
ovcacn10r1 Network Configuration Analysis -- FAIL
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |