Goal

How to determine what the Purchase Order (PO) Price and/or Merchandise Amount (encumbrance amount) was initially, prior to a change.

When a PO is created and Budget Checked, the amounts for the PO Line can be seen in KK_ACTIVITY_LOG. But when the amount is changed and Budget Checked again, the amount on KK_ACTIVITY_LOG is overwritten. How can you determine the original PO Price in a situation like this?