PeopleSoft Enterprise Project Costing: PC_STAT_LINK SHOULD BE ENHANCED TO ALSO PROCESS ACTIVITIES

(Doc ID 1309335.1)

Last updated on SEPTEMBER 15, 2016

Applies to:

PeopleSoft Enterprise FIN Project Costing - Version 8.9 to 9.1 [Release 8.9 to 9]
Information in this document applies to any platform.

Symptoms

The activity processing status is not looking at the effective date of the activity status. So when a future dated Closed status is added on the Activity Status page, the engine PC_STAT_LINK is not updating the Activity Processing Status to Inactive, when the current date reaches the future date.

Cause