EAP: Voucher Build is assigning Schedule Due Date as Current Date when using Net 30 Payment Terms (Doc ID 1316989.1)

Last updated on SEPTEMBER 15, 2016

Applies to:

PeopleSoft Enterprise FIN Payables - Version: 9 to 9.1 - Release: 9 to 9
Information in this document applies to any platform.

Symptoms

Voucher Build is assigning Schedule Due as Current Date when Net 30 Payment Terms are used. Online Vouchers calculate the Schedule Due date correctly.

STEPS
1.  Create a Quick Invoice with an Invoice date of 03/27/2011 and Payment Terms as Net 30
2.  Run Voucher Build
3.  Notice that the Schedule Due date is populating as the Current Date

Cause

Sign In with your My Oracle Support account