EAM: Leased Asset-Express Add When Entering Information and Then Changing any Variable You Are Forced to Clear the Cost or MRP (Doc ID 1470102.1)

Last updated on APRIL 25, 2016

Applies to:

PeopleSoft Enterprise FIN Asset Management - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

Update Lease Information forces you to clear either the cost or MRP.

EXPECTED BEHAVIOR
-----------------------
When making a change to a lease and clicking Calculate, there should be no messages.

STEPS
-------
The issue can be reproduced at will with the following steps:

1. Go to Lease Assets Express Add

2. Enter lease information, click on Calculate
3. Update say the interest rate
3. Click Calculate

Cause