Incorrect Req Status after PO Cancelled and Resourced (Doc ID 1564402.1)

Last updated on MAY 31, 2017

Applies to:

PeopleSoft Enterprise SCM eProcurement - Version 9.1 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

On : 9.1 version  Requisition

ACTUAL BEHAVIOR
---------------
Incorrect Req status after PO cancelled and resourced . Requisition shows status of Partially Received if a PO associated with requisition is cancelled and other PO is dispatched and received.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1.Navigate to ePro-Create Requisition-Save and Submit

2. Expedite Requisition

3. Check the PO created-Dispatch the PO

4. Cancel the PO-Select Resource the Requisition while cancelling the PO

5. Expedite the Requisition again

6. Dispatch the PO

7. Receive the PO fully

8. Check the ePro requisition status


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms