Symptoms

PO that is increased above the tolerance limit will correctly have a Doc Tol Status = Error.
However, if the User first finalizes the Req Line from the PO Line and budget checks the PO, and then increases the PO above the tolerance limit, the Doc Tol Status will incorrectly stay Valid rather than going to Error status.


The issue can be reproduced at will with the following steps:
1 - Create a Requisition and validate KK
2 - Create PO copy from requisition above.
3 - Keep the PO amount equal to the Req amount and save PO
4 - Validate PO KK (KK status and tolerance should be valid)
5 - Increase PO amount to amount greater than tolerance value.
6 - Validate kk… received the message tolerance. (KK status is valid but tolerance status is error)
7 - Reduce PO Amount back to the original Req Amount.
8 - Validate PO KK (KK status and tolerance should be valid)
9 - Click the Finalize button on PO Line 1 Details page.
10 -Increase the PO Amount to an amount that will exceed the Req to PO Tolerance. Budget check.
11 -KK status = valid and Doc tolerance = valid. Doc Tolerance status should be = ' error'.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms