Change Request Process is Creating a new Purchase Order (PO) when Adding a Line to the Requisition (REQ) (Doc ID 1596977.1)

Last updated on JANUARY 04, 2017

Applies to:

PeopleSoft Enterprise SCM eProcurement - Version 9.1 and later
Information in this document applies to any platform.

Goal

When we create a change request by adjusting an existing line on an ePro requisition, the process change request correctly updates the existing PO line. If we create a change request by adding a new line to an ePro requisition, the process change request creates a new PO instead of adding the line to the existing PO.

 

Shouldn't this line just be added to the existing PO?
 

Solution