Could not update un-completed tasks in Sourcing Plan (Doc ID 1680292.1)

Last updated on JANUARY 19, 2016

Applies to:

PeopleSoft Enterprise SCM Strategic Sourcing - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

ISSUE:
--------
Active tasks in Sourcing Plan could not be updated.

Actual Behaviour:
---------------------
When a Sourcing Plan with multiple tasks, the uncompleted tasks are not available for update

Expected Behaviour:
-------------------------
When a Sourcing Plan with multiple tasks, the uncompleted tasks should be available for update

Steps:
Create a sourcing plan, plan details add multiple tasks(2 tasks), save and post plan.
Update task 1, task 2 remains 'not complete' and save
Go out of the component and back in, bring up the sourcing plan

Cause