EPGM9.2: Able To Change Assignment Start Date To Date Earlier Than Job Effective Date (Doc ID 1906183.1)

Last updated on SEPTEMBER 15, 2016

Applies to:

PeopleSoft Enterprise FIN Program Management - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

1) Create a resource in Resource Management. The job effective date is 06/06/2014.
2) Create a project and activity with Start Date 01/01/2013 and End Date 12/31/2015.
3) Assign the resource to the project. The Assignment Start Date is 06/06/2014 and Assignment End Date 06/30/2014.
4) Open the Resource Detail page in Project Costing and change the Assignment Start Date to 06/01/2014.

PROBLEM: the system should not allow us to change the assignment start date to a date earlier than the employee's job effective date on the table PS_RS_WRKR_EFFDT. The employee's job effective date is 06/06/2014, so the system should not allow us to change the assignment start date to 06/01/2014.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms