As Incurred Bill Plan Status Was Changed From In Progress to Completed. How Can We Bill More Transactions? (Doc ID 1921016.1)

Last updated on MARCH 09, 2017

Applies to:

PeopleSoft Enterprise FIN Project Costing - Version 8.9 to 9.2 [Release 8.9 to 9]
PeopleSoft Enterprise FIN Contracts - Version 8.9 to 9.2 [Release 8.9 to 9]
Information in this document applies to any platform.

Goal

Can we change the status of a bill plan from 'Completed' to 'In Progress'?

We had an invoice problem due to amount equal to tolerance amount. To fix this issue, we have unknowingly modified the bill status to 'completed'. Now, we have more transactions we want to bill but cannot because the bill plan status is Completed.
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms