ISSUE:
--------
Release Amount is getting calculated wrong in Procurement Contract pages if PO Line has negative Amt

Steps:
-------
1) Created the Contract with max amount as 100 USD
2) Created a PO with 4 PO Lines, two of which are negative amounts.
3) Opened the Events page in Procurement Contracts. Release Amount value is wrong.

Cause