EPGM9.2: PeopleSoft Project End Date Being Updated With Primavera Activity End Date When Activity End Date Falling Before Project End Date (Doc ID 1954188.1)

Last updated on SEPTEMBER 15, 2016

Applies to:

PeopleSoft Enterprise FIN Program Management - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

In PeopleSoft the project end date is 12/31/2014. Add an activity in Primavera with an end date 11/15/2014. Run the Synchronize Existing Projects. Notice that the project end date has been updated to 11/15/2014 in PeopleSoft, which is wrong. It should have remained 12/31/2014.

Cause