Symptoms

When you update the activity end date of an existing activity in Primavera (P6) to a date greater than the project end date in PeopleSoft (PS), then when the engine PGM_SYNC_PRJ (Synchronize Existing Projects) is run, the project end date in PS is not getting updated.

For example: suppose the project end date in PS is 30-Dec-2016. Then the activity end date of an existing activity in P6 is updated to 10-Oct-2017 and the engine PGM_SYNC_PRJ is run. The project end date in PS is still 30-Dec-2016, but it should have been updated to 10-Oct-2017.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms