No Planned Supply Generated by the 'MRP Solver' Process (PL_RUN_MRP) for Components Used at Multiple Operations on a BOM and One Operation Has No Planning Time (Doc ID 1981870.1)

Last updated on AUGUST 04, 2016

Applies to:

PeopleSoft Enterprise SCM Supply Planning - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

If a Component exists multiple times on a Bill of Material (BOM multiple times (i.e. used at multiple Operations) and the 'Qty Per' for that Component is the same at each Operation and at least one of the Operations has no Planning Time, the 'MRP Solver' process (PL_RUN_MRP) (navigation: Supply Planning. Solve Plan, Initiate Material Solver) does not generate a Planned Supply for Component demand at the Operations with no Planning Time.

Changes

 

Cause