The 'MRP Solver' Process (PL_RUN_MRP) Creates Incorrect Planned Orders when an Item Is Below Safety Stock at the Early Fence and Existing Supply Is Available after the Early Fence (Doc ID 1995338.1)

Last updated on AUGUST 04, 2016

Applies to:

PeopleSoft Enterprise SCM Supply Planning - Version 8.8 SP1 and later
Information in this document applies to any platform.

Symptoms

The 'MRP Solver' process (PL_RUN_MRP) (navigation: Supply Planning. Solve Plan, Initiate Material Solver) is creating incorrect Planned Orders when an Item is below Safety Stock at the Early Fence AND existing Supply Order (ex. Purchase Order) is available some time after the Early Fence. If the process is run without the 'Allow Cancellations' option, then in addition to the existing Supply Order(s) a new one is planned.

Changes

The issues occurs after installing:

<Patch 17539678> (PT 8.53.09 PRODUCT PATCH) (Update ID 901382)
or
PeopleTools 8.54.00

Cause

Sign In with your My Oracle Support account