Requisition Change Request Lines in "Budget Not Checked" Status (Doc ID 2005662.1)

Last updated on FEBRUARY 26, 2017

Applies to:

PeopleSoft Enterprise SCM eProcurement - Version 9.1 to 9.1 [Release 9]
Information in this document applies to any platform.

Symptoms


Change Request lines in "Budget Not Checked" Status  

We are seeing the change request lines( Increase in quantity) getting into "budget not checked" when it is save and submitted even when the project id is blank. When the line quantity is increased by another +1 and performed the save/submit, the change request is changed to "Ready for Process".

Replication Steps


 1) Create a requisition, budget check
 2) save/submit, self approve the requisition
 3) Source to a PO.
 4) Budget check and dispatch the PO.
 5) Edit the requisition to increase the line quantity¿
 6) on Save and Submit FS_BP is triggered and not changing the budget status
 7) As shown here the budget status did not change¿on the workflow page the
 user is clicking the "Check Budget" button and FS_BP is triggered.
 8)> Status is changed from Budget not checked to Ready for Process
    > why FS_BP is not changed the status to "Ready for Process" in the first place (Save and Submit -FS_BP).

Due to this issue, users cannot effectively do change orders with budget check

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms