Symptoms

FS_BP is not picking up the purchase orders processed by PO Roll 1.


After running PO Roll 1, it is required to run the Budget Check process before proceeding.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Ran PO Roll View for PO Dates = 7-1-2014 through 6-30-2015.
2. Selected 54 purchase orders on the Roll Workbench. Clicking PY Encum Close
3. Run FS_BP by Business Unit.


Cause