On : 9.1 version, Functionality

ACTUAL BEHAVIOR
---------------
Program Management is turn on and Maintenance Management off. Tab Order is Incorrect in Project General Information. After tabbing out from Percent Complete, it focus goes to "Calculate" field in Project Schedule section..

EXPECTED BEHAVIOR
-----------------------
Program Management is turn on and Maintenance Management off. Tab Order is Incorrect in Project General Information. After tabbing out from Percent Complete, it focus should go to next field which is "User Defined" field in Project Health section.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Turn Program Management on and Turn off Maintenance Management in the Set up Financial Supply Chain > Install > Installation Options - Products
2. Navigate to Grants > Awards > Project or Project Costing > Project Definition > General Information
3. Open an existing Project
4. Get the cursor to Percent Complete field.
5. Tabbing out will take the next focus field as "Calculate" field in Project Schedule section.

It should be "User Defined" field in Project Health section.

Apart from the above specific use case, there are other tab order issues on this tab as well as in other tabs of Project definition. 



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms