My Oracle Support Banner

EMM: PM Schedule Mass Update Process Goes In The Infinite Loop (Doc ID 2024643.1)

Last updated on MARCH 09, 2017

Applies to:

PeopleSoft Enterprise FIN Maintenance Management - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

PM Schedule Mass Update process goes in the infinite loop while performing update for three or more schedules for the following parameters
1. Blackout Period
2. PM Linking
3. Meter-based Schedule

Steps to recreate the issue
1. Create three or more PM schedules for three different scenarios listed below
- With blackout period.
- With PM Linking option
- With the meter-based parameters
2. Run the PM Schedule Mass Update process for the above scenarios

Result: Process goes in the infinite loop while updating the second schedule and never finishes.


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.