Bill Plan And Revenue Plan Hold Designation Being Removed By Amendment When The Plan Status is Ready and Events are Created Using Define Events = Percent (Doc ID 2036998.1)

Last updated on MARCH 09, 2017

Applies to:

PeopleSoft Enterprise FIN Contracts - Version 9.1 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

Amendment removed HOLD designation on Milestone bill plan when Define Events set to Percent

Replication steps:
1. Create a contract with amount based line and billing method as method as milestone. (Create the bill events using Define Events = Percent. Event can be Dates or Milestones)
2. Contract is made active
3. Set the Ready bill plan to HOLD
4. Amend the contract. Change the amount allocation.
5. Set the amendment to ready
6. Process amendment --> HOLD checkbox is removed.

Same replication for Revenue Plan

Expectation:
We need to have the Hold designation only be removed by the user.

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms