EPY: Contract Pay - Conversion Data from 9.0 to 9.2 does not Match (Doc ID 2054011.1)

Last updated on OCTOBER 15, 2015

Applies to:

PeopleSoft Enterprise HCM Payroll for North America - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

Carry over amount is wrong

Expect the carry over amount to be the same as the goal balance in 9.0

When an employee has 2 jobs, 2 contracts. Emp rcd 0 and 1. Both contracts are identical. They also use single check for multiple jobs. So the paylines are combined on the higher payline. The carry over amounts are doubled.