Why Planned Purchase Orders Are Created when Material Stock Requests (MSR) Are Picked/Shipped but Not Depleted Yet from Non-Nettable Locations (Doc ID 2069928.1)

Last updated on JANUARY 13, 2018

Applies to:

PeopleSoft Enterprise SCM Supply Planning - Version 8.8 SP1 and later
Information in this document applies to any platform.

Goal

You observe that the 'MRP Solver' process (PL_RUN_MRP) (navigation: Supply Planning. Solve Plan, Initiate Material Solver) creates Planned Purchase Orders when Material Stock Requests (MSR) are created and picked/shipped but not depleted yet and the quantity is picked from non-Nettable Storage Locations. Why is that?

Steps to replicate the issue:

  1. Create two Storage Locations, one Nettable and one non-Nettable.
  2. Configure two new Items for Supply Planning and set a Safety Stock for each Item to 15.
  3. Putaway a quantity of 50 for the first Item to the Nettable Location and a quantity of 50 for the second Item to the non-Nettable Location.
  4. Perform an Express Issue of 40 for both Items, but don't deplete the quantities yet.
  5. Perform the Planning Cycle and run the PL_RUN_MRP and observe a Planned Purchase Order of 5 for the Item issued from the Nettable Storage Location (expected) and a Planned Purchase Order of 55 for the Item issued from the non-Nettable Location (UNEXPECTED).

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.