Pre-encumbrance not Liquidated when Requisition is Sourced to Sourcing Event, then Awarded to Contract and PO created from Contract Release (Doc ID 2073606.1)

Last updated on JANUARY 13, 2017

Applies to:

PeopleSoft Enterprise SCM Purchasing - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

Pre-encumbrance not Liquidated when Requisition is Sourced to Sourcing Event, then Awarded to Contract and PO created from Contract Release.


1)  Create a requisition.  Budget check.  Pre-encumbrance is created.
2)  Copy req into a Sourcing Event.
3)  Award Sourcing Event to a Purchase Order Contract.
4)  Create a Contract Release.
5)  Run Stage Contract POs process.
6)  Run PO Calculations process.
7)  Run PO Creation process.
8)  Open the Purchase Order distribution and see that Req ID is not there.
9)  Budget check the Purchase Order.  Encumbrance is created.
10) Open the Requsition and see that the Pre-encumbrance is not liquidated.

NOTE: This works correctly in release 9.1 but not working in 9.2.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms