Symptoms

Change request to cancel multiple scheduled Requisition line issue

Steps to Reproduce the Issue:
1) Create an eProcurement Requisition with 1 line and 10 schedules
2) Budget Check , Approve and Source it
3) Dispatch the Purchase Order
4) Change Request to cancel the Requisition Line

Purchase Order's only Last Schedule gets cancelled

Workaround: cancel directly in Purchase Order