EMM: ONLY ONE TASK DISPLAYS IN LABOR ACTUALS GRID (Doc ID 2106963.1)

Last updated on MARCH 15, 2016

Applies to:

PeopleSoft Enterprise FIN Maintenance Management - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

Labor Actuals do not show data of all tasks on the Work Order Cost page.

Business Impact:
Cannot see all tasks associated to a WO.


1. Create a Work Order with 2 tasks.
2. Assign labor to both the tasks.
3. Go to the Cost page, and verify if the labor Actuals grid shows data for both the tasks.

Expected Results:
Expected to see all tasks associated to the WO.

Actual Results:
Only see 1 task associated to the WO.

Cause