Some Activity Updates Automatically Update Project Dates But That Is Not Calling The PROJECTS_SYNC Integration To Update HCM (Doc ID 2119488.1)

Last updated on MARCH 09, 2017

Applies to:

PeopleSoft Enterprise FIN Project Costing - Version 9.1 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

Updates to a project should call PROJECT_SYNC integration service to send the updates to HCM. However, when an activity end date is updated past the project end date, the project end date is updated automatically but PROJECT_SYNC is not called. For consistency, PROJECT_SYNC should be invoked.

This can be reproduced as follows:

  1. Navigate to an existing project and note the project end date.
  2. Drill down on the project activities.
  3. Update an activity end date to push it out past the current project end date.
  4. Save. Return to the project and note the end date has been updated.


Due to this issue, project data in HCM may be out-of-sync with Financials and therefore payroll expenses incurred even though a project has expired.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms