Program Management/Project Request Workflow Final Approver On First Approver (Doc ID 2144741.1)

Last updated on JUNE 15, 2017

Applies to:

PeopleSoft Enterprise FIN Program Management - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Goal

On : 9.2 version, Project Request Approval Functionality

ACTUAL BEHAVIOR
---------------
Program Management/Project Request workflow final approver on first approver even there are other approvers visible in the workflow

EXPECTED BEHAVIOR
-----------------------
It should set to approved only after all approvers have approved

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Add another step in delivered PGM_PROJREQUEST with Always True criteria
2. Add project request
3. Once 1st person from step 1 approved the worklist, it sets the project request to approved even the approval from 2nd step is still pending.


 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms