PO_LINE_SHIP.CONVERSION_RATE is set to 0.00 by the PO_POCHNG Process. (Doc ID 2170338.1)

Last updated on JANUARY 30, 2017

Applies to:

PeopleSoft Enterprise SCM Purchasing - Version 9.1 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

The PO_LINE_SHIP.CONVERSION_RATE values are missing after running PO Close Short.  Part of running the Close Short process is the PO_POCHNG process.  After the PO_POCHNG process is run, the PO_LINE_SHIP.CONVERSION_RATE value is updated to 0.00

The issue can be reproduced at will with the following steps:

1. Create a purchase order for quantity 30. Split this into 3 equal schedules of 10 ea. Dispatch the PO.

2. Create 3 receipts, receiving schedules as follows: Receive Schedule 1 in full. Receive Schedule 2 - quantity 8. Receive Schedule 3 - quantity 7 in 3 separate receipts. (30 ordered, 25 received)

3. Create 3 vouchers, vouchering each receipt.

4. Query PO_LINE_SHIP and confirm CONVERSION_RATE = 1.000 for each line/schedule.

5. Run the PO Close Short process

6.Approve the Change Request

7. Run the PO_POCHNG process

6. Re-Query PO_LINE_SHIP and now notice that the CONVERSION_RATE = 1.000 for row 1 and is blank for Rows 2 and 3

 

Cause

Sign In with your My Oracle Support account