Cost Rollup Process Calculating Incorrect Cost On Items That Have Co-Products In Their BOM (Doc ID 2176239.1)

Last updated on AUGUST 25, 2016

Applies to:

PeopleSoft Enterprise SCM Manufacturing - Version 9.1 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

Cost Rollup Process Calculating Incorrect Cost on Items that have Co-Products in their BOM

The issue can be reproduced at will with the following steps:

1. Setup the BOM

BOM A Item is a co-product of the BOM
BOM B Item is a component of the BOM

The following is noticed when doing a cost roll up for the top level items using the above BOM setup

2. Run Cost Rollup process
a) If each item is cost rolled separately, costs are calculated correctly.
b) If the items are cost rolled at the same time, the second item (using BOM B) is calculated with a cost that has been lowered by an amount equal to the costs associated to the component which is also used as a co-product on the other BOM

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms