Symptoms

Cost Element override is stopping project costing records from going to proj_resource.

Doc ID 1987688.1 states changes made to stop overrides of inbound costs, which was included in Release 9.2 - Bug 19855131. This change also stopped all project costing overrides from being made and carried forward to proj_resource.  Problem apparent when having to issue make items to different projects and then bill customers using markup percentages.  With the new change, only material cost elements carry forward the project information. All other cost elements are dropping the project overrides and therefore not posting to proj_resource.

Steps to reproduce the issue:
If item has cost elements 100 - Material, 200 - Labor, 300 - Overhead and we issue it to project 10000 using chartfield overrides as the project could be different every time, only the cost element 100 will have the project information in CM_ACCTG_LINE and therefore post to proj_resource. However all the cost element are required to make up the total cost of the item.


Changes

Not applicable. 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms