How Is Due Date on PO Calculated if The Due Date on The Requisition is Given As Past Date?

(Doc ID 2203324.1)

Last updated on JUNE 16, 2017

Applies to:

PeopleSoft Enterprise SCM Purchasing - Version 9.2 and later
Information in this document applies to any platform.


This document explains how the Due Date value on a PO is calculated if the due date on the requisition is in the past


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms