ETL9.2: TimeSheet Apply Schedule Does Not Work For Week After Cancel Changes (Doc ID 2213174.1)

Last updated on JANUARY 09, 2017

Applies to:

PeopleSoft Enterprise HCM Time and Labor - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

On : 9.2 version, Technical

ACTUAL BEHAVIOR
---------------
Timesheet Apply Schedule does not work for Week after cancel changes

EXPECTED BEHAVIOR
-----------------------
Timesheet Apply Schedule should work for Week after cancel changes

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Click apply Schedule in timesheet page
2. A week data is populated based on schedule assignment data.
3. Change view by option from "Week" to "Day" at Select Another Timesheet Grid.
4. Do not save changes. Click Cancel when message box is displayed.
5. The screen is correctly changed to Day with its attributes.
6. Change view by option from "Day" to "Week"
7. The screen is correctly changed to Week with its attributes.
8. Click apply Schedule in timesheet page

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms