STATEMENT
-----------------
The absence duration is incorrect when user select "Start and End Days" option and only checked on "Start Day is Half Day" or "End Day is Half Day" either.

STEPS TO REPLICATE
---------------------------------
1. Apply partial day leave from Navigation ESS-->Time Reporting-->ReportTime--> Absence request
2. Select Partial Days Start and End Date and End day is Half day checkbox should be checked (or Start Day checked).
3. Verify duration calculated.

EXPECTED AND ACTUAL BEHAVIOR
----------------------------------------------------
Actual:The Duration field calculates incorrect value.
Expected:The Duration filed must be calculated with accurate value based on the selection.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms