Symptoms

Cannot add a new distribution line for a rolled PO on Maintain Distributions page but able to add/update distribution line on PO Add/Update page.
Able to add/update distribution line on a PO that is not rolled on Maintain Distribution page. 

STEPS
The issue can be reproduced at will with the following steps:
1 - Create PO date 02/28/2016, accounting date and budget date = 02/28/2016
2 - Validate KK and Dispatch
3 - Create voucher for 2016 partially
4 - Validate KK and Posting Voucher
5 - Run Request PO Roll View
6 - PO Rollover Workbench
7 - Run Request PO Roll Open Encumbrance
8 - Back to PO:
  - Distribution line created
  - Buttons ‘+’ and ‘-‘ is not appearing for PO that rolled.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms