HR: Job Data Changes Are Not Reflected In Contracts (Doc ID 2258231.1)

Last updated on APRIL 24, 2017

Applies to:

PeopleSoft Enterprise HCM Global Payroll Spain - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

On : 9.2 version, General

ACTUAL BEHAVIOR
---------------
Contract dates incoherent with Job data

Changes from Job Data are not reflected in Contracts (Update Contracts component)


EXPECTED BEHAVIOR
-----------------------
The dates from PS_WKF_CNT_AFI should be changed with the new dates from Job Data

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Add termination on 16 August 2016 for an employee
2. Rehire the employee with the same date (16 August 2016), effective sequece=1, add Next Contract Number
3. Go to Update Contracts and update the new contract with contract type
4. Add Termination on 31 October 2016 for the same employee. The contract is updated with Contract End Date
5. Change first termination date (from 16 August 2016 to 01 July 2016), change rehire date from 16 August 2016 to 01 July 2016
6. Change termination date from 31 October to 31 July 2016 (before the initial rehire date 16 August)
7. Go to Update Contracts, all the dates are changed except the end date for the new contract.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms