Cannot Cancel a PO Line Receive Error: Cannot cancel this req line because associated PO have this as only active schedule line (10111,19) (Doc ID 2259499.1)

Last updated on SEPTEMBER 26, 2018

Applies to:

PeopleSoft Enterprise SCM eProcurement - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

Unable to Cancel a PO Line via Change Request Process. This functionality was working in Image 16. Client recently applied Image 22 and now it seem to be broken.

Create requisition with 2 lines and source to PO. When try to cancel any of the lines, its not allowing instead its throwing a message "Cannot cancel this requisition line because associated PO have this as only active schedule line. (10111,19)".

 Steps to Replicate:

1. Create a two line requisition using Special Request
2. Approve and Budget Check Requisition
3. Source the Requisition to a PO
4. Budget Check and Dispatch the PO
5. Trying to create Change Request (Cancel Line 1) using Manage Requisition

System gives the following error:

Cannot cancel this requisition line because associated PO have this as only active schedule line. (10111,19)

Changes

The issue was caused by changes made by Image 22 and Bug 23730567.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.