PO_PORECON Process Not Picking Up the PO's for Closure With Multiple Schedules and Distribution Lines (Doc ID 2276611.1)

Last updated on JUNE 13, 2017

Applies to:

PeopleSoft Enterprise SCM Purchasing - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

Issue:-The PO close process does not pick PO's which are vouchered and matched and have multiple distribution lines.


Steps To Reproduce the Issue:-
1) Create Purchasing Requisition and then source it to PO with 1 line 2 schedule and 2 distribution in each schedule.
2) Create receipt and edit the receipt to put more Qty/Price in distrib line one but total QTY/AMT should not be more than the PO ship line.
3) Create Vouchers for these receipt and run voucher match and posting.
4) Run PO close process.

The PO is not picked for closure.

PO line was not closed due to the error
"POs with Receiving Required On though not fully received and No Tolerance set."

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms