Buyer ID Doesn’t Transfer From Award Details Page To Contract Entry Page (Doc ID 2282363.1)

Last updated on JUNE 30, 2017

Applies to:

PeopleSoft Enterprise SCM Strategic Sourcing - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

On : 9.2 version, Award Events

Buyer ID doesn’t transfer from Award Details page to Contract Entry page when Event is awarded to a Contract. Test case document attached.


The issue can be reproduced at will with the following steps:
1. Create an Event as Event Administrator
a. Select Header Bid Factors
b. Enter Line Information
c. Set Dates and Times
d. Select Bidders to be invited
e. Post the Event
2. Post Bid
a. Login as the Invited Bidders on Supplier Portal
b. Post Bids before end time of the event
3. Analyze Event
a. Log in as the Event Administrator
b. Navigate to Event Workbench
c. Analyze the bids submitted by the Bidders
d. Award Bid to two of the Bidders and put 50% as award percentage for each bidder
4. Award Event
a. Select Award Event from Go To dropdown menu on Analyze events page
b. Select Procurement Contract as Award Type
c. Select General Contract as Contract Style
d. Enter required values including the Buyer
e. Click on Post Award button
5. Contract Entry
a. New Contract Entry page is created
b. Buyer should be populated on the Contract Entry. This should have been passed on from Award Events page



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms