Symptoms

Commitment control budget checking process (FS_BP) abends at FS_BP_FSRC.iFSLqdTO.uFSLqdTO with below error:

 

 

Steps to Replicate:

  1. Create a PO with two lines. Set the Receiving Required as Optional. Set the GL BU.Populate the PC BU, Project ,Activity and Budget Check and Dispatch the PO.
  2. Create a Voucher by copying the first PO line with partial quantity.
  3. Again add a line by copying the first PO line with the remaining quantity. Thus voucher is created with two lines.
  4. Budget check the voucher.
  5. Now delete the second line on the voucher
  6. Add a new line by copying the second PO line.
  7. Save the Voucher.
  8. Run Budget Check.


See the replication screenshots for more details.


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.