Symptoms

Numbers are getting displayed in place of dates in the Schedule Chart of any resource, after upgrading PeopleTools to 8.54.

Steps:
--------
The issue can be reproduced at will with the following steps:
1. Navigation:1 Main Menu > Resource Management > Interactive Reports > Chart Resource Schedules
2. Add a new Run Control Id
3. Chart Resource Schedules page will appear.
4. Enter Start Date and click on 'Go to Parameters' link to enter input parameters
5. Click on Go back to Resource Schedules
6. Click on Generate Report

Actual Result:
-----------------
The Resource Schedule chart represents the schedules of the resources who appear in the active filter. The chart displays schedules for a four-week period beginning with the current date, and navigation icons to scroll to the next or previous four-week period.

However, chart is displaying incorrect values on both axis. Please refer to attached document.

Expected Result:
--------------------
Chart should display correct values on both axis
 

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms